Site area
177 acresFormer power-station redevelopment site; not all of Lakeview. [2]
City project descriptionMississauga · Peel Region
A former power-station site is becoming a waterfront neighbourhood with homes, employment space and a connected park system. This guide separates the evolving build-out plan from zoning capacity and identifies which improvements are underway, planned or still dependent on later approvals. [2] [12]
Planning picture Servicing and first residential construction underway; later blocks and public amenities are phased
Lakeview Village is the 177-acre former power-station site on Mississauga’s eastern waterfront. Rangeview has its own master plan; its homes must not be added to Lakeview Village or represented as phases of the same site. [2] [13]
Site area
177 acresFormer power-station redevelopment site; not all of Lakeview. [2]
City project descriptionCity’s current build-out description
12,000 homesThe project page describes 800 affordable or attainable units within this total. This is a programme description, not proof that the zoning ceiling changed. [1]
Source checked October 2026; page gives no revision date2023 zoning permission
16,000 unitsProvincial zoning-order permission, distinct from the current 12,000-unit project description. [3]
May 12, 2023 orderPark programme
18.5 hectares / 45.73 acresSix planned parks, including Waterfront Park, Cultural Pier, Ogden Park, Aviator Park, Waterway Common and Lakeview Square. [5]
City park projectInnovation employment target
Over 9,000 jobsIDEA promotes a future employment district, not jobs already operating on site. [6]
Undated IDEA project page, checked October 2026The redevelopment combines residential blocks with an innovation and employment district, waterfront public spaces, and ground-level destinations. The developer presents arts, culture, sustainable infrastructure and walkable public space as organising ideas. Treat renderings and programming concepts as the intended neighbourhood experience, rather than evidence that every venue is funded or open. [12]
The planning framework was endorsed on November 6, 2019. Individual buildings still have their own plans, permits and delivery schedules. That distinction matters when comparing a home approaching construction with an unlaunched future block. [4]
The City’s October 2024 account describes the original 2021 zoning for 8,050 units. Ontario’s May 12, 2023 order allowed 16,000. The current municipal project page describes 12,000. These are successive planning figures for the same community, not three phases to add together. No reopened source establishes that 12,000 has replaced 16,000 as the legal maximum. [2] [3] [1]
Tridel’s August 2026 construction report says Harbourwalk forming had reached Level 8 and ground-floor window installation had begun, with mechanical, electrical and masonry work in the underground levels. This is dated evidence of a building progressing, not a completion certificate or an occupancy guarantee. [8]
The City reports utilities and roads underway. It forecasts initial occupation in early 2029 using natural-gas district energy, with a proposed wastewater-energy transition in 2034. These forecasts do not replace a building’s contractual occupancy schedule. [1]
The park programme links internal green spaces with the lakefront and a Cultural Pier extending approximately 350 metres into Lake Ontario. The Waterfront Trail and pedestrian-bridge environmental study reached a November 2025 completion notice, with comments due January 15, 2026. The staged park programme does not establish one opening date for all six spaces. [5]
The neighbouring Jim Tovey Lakeview Conservation Area opened in 2026 and adds 26 hectares of conservation land. It is a separate waterfront asset: its area is not extra Lakeview Village development land or part of the six-park acreage. [10]
IDEA markets over 1.8 million square feet of employment space and over 195,000 square feet for retail; the City gives an employment-space minimum of 1.5 million. These planning measures are not occupied floorspace. [6] [1]
The 2024 agreements address housing tenure, community benefits, transportation improvements, odour and noise mitigation, and land for a Peel District School Board school. A reserved school site does not confirm a funded school, opening year or assignment for a particular address. [2]
The Lakeshore BRT project reviewed by the City covers about two kilometres between Etobicoke Creek and East Avenue. Its transit environmental assessment was completed in 2023. The reviewed page does not confirm an opening date, so future BRT should be a separate consideration from today’s journey to work. [9]
Enwave’s October 2024 groundbreaking announcement describes central heating and cooling infrastructure and a planned operations centre, Peel sewage pumping station and educational space. Treated wastewater from G.E. Booth is an intended future energy source. This changes how the community will be serviced, but it does not establish a household’s eventual utility bill. [7]
Caivan explicitly locates Aura within Lakeview Village and describes two-storey townhome designs. DECO and OPUS identify South Banks as another Lakeview Village townhome collection. These are meaningful within-community links; the shared sales-gallery address alone would not establish a project boundary. [14] [15]
A future target is a forecast. It is not a promised completion or move-in date.
Council endorsed the development framework. [4]
Ontario filed the order permitting 16,000 units. [3]
Enwave and public partners marked the start of the district-energy project. [7]
The City reported the Jim Tovey Lakeview Conservation Area open to visitors. [10]
The builder reported forming at Level 8. [8]
No. That figure is the City’s description of the planned development. Harbourwalk’s dated construction report confirms an early residential phase is still being built. [1] [8]
No. Rangeview has a separate master plan. Use the named development site and builder evidence when comparing listings. [13]
FOLLOW THE DECISIONS
Within the area · Caivan explicitly identifies Aura as part of Lakeview Village. [14]
Within the area · The official DECO/OPUS project site identifies South Banks as a Lakeview Village collection. [15]
Browse all Mississauga projects ↗. This city-wide list includes projects outside the planning area.
Official sources establish the facts; our synthesis explains how their dates, boundaries and decisions fit together. Planning capacity is not completed housing or available inventory.